Areva updates us on progress at Olkiluoto

Share  
 
   

So how are things going at the construction site of the OL3 EPR reactor at Olkiluoto in Finland? The builders, Areva, can update us…

Sounds like it’s all going perfectly well. No mention of the three year delay until the reactor is completed or the nearly two billion euro cost of that delay. Funny that.

There’s also a curious figure on Areva’s blog concerning the number of people working to complete the OL3 EPR: 3,500 to be precise. That’s quite a different number from the 9,000 UK environment minister Ed Miliband said each new EPR in the country will provide. Who’s right? As ever when it comes to nuclear power, don’t trust the numbers.

Comments

It was not a super-reasonable spending.

Maybe Bulgarians will do different!!


"SOFIA (Reuters) - Bulgaria's new center-right government must find private investors for its majority stake in the planned Belene nuclear power plant or abandon the project, parliamentarians said on Thursday. "

http://www.reuters.com/article/scienceNews/idUSTRE56T3X720090730