Nukes are a dangerous waste of time and money
How this works:
The accumulating costs above are based on the EUR 1.7 billion overrun announced by Areva/TVO plus an extra EUR 1.2 billion which will be needed to purchase electricity that has not been produced by Olkiluoto-3 since its projected start.
These costs will eventually be paid for by Nordic electricity consumers and French taxpayers, either through higher bills for customers or through taxes.